Интерактивная карта лучших практик

по использованию водных, земельных и энергетических ресурсов,
а также окружающей среды Центральной Азии

Сравнение практик

Название практики Introduction of Integrated Water Resources Management (IWRM) principles on the Isfara small transboundary river Resource-saving technology of operating vertical drain-age wells based on drainage water re-use in irrigated massifs
Категория Водные ресурсы Водные ресурсы
Инструмент Принцип общественного участия
Сфера использования практики
  • Use of water resources
  • Use of land resources
  • Use of water resources
  • Use of land resources
  • Re-use of drainage water for irrigation
Пригодность практики для адаптации к изменению климата Высокая Умеренная
Кем реализована практика USAID/CAREC
Kazakh Scientific Research Institute of Water Economy (KazSRIWE) LLP
Где использована практика

Страна: Кыргызстан

Страна: Казахстан

Область: Южно-Казахстанская

Район: Мактааральский

Другой населенный пункт: Zhanaauyl Rural District

Специфика местности, где использована практика

Transboundary river

The Maktaaral Irrigation Massif has 220 vertical drainage wells (VDW), but currently practically all of them are not operational.   The highest level of ground water occurrence in Maktaaral Irrigation Massif falls on December-February after completion of fall irrigation washings and water-charging.  The beginning of vegetation season (April-May) is characterized by receding ground water table.

The second ground water table rise occurs during mass vegetation watering of main crops, as a rule in July-August.

The vertical drainage system in Maktaaral Irrigation Massif does not operate on permanent basis, but mainly during fall and winter (irrigation washing, water charging) and during the vegetation season at the time of insufficient irrigation water supply.

Когда использована практика

Дата начала: 01.04.2012

Дата окончания: 31.10.2016

Дата начала: 01.01.2016

Дата окончания: 31.10.2017

Проблема, которая решается применением практики

Imperfections of the water management mechanism in the Isfara small transboundary river basin

Deterioration of reclamation situation: raising ground water table and land salination.  Intensified water withdrawal, saving on pipes, reusing ground water for irrigation

Примененные в практике инструменты

The principle of stakeholder engagement in decision-making associated with water management of small transboundary river;

IWRM planning technique

Set of measures to enhance land reclamation condition (rehabilitation of vertical drainage well capacities, fitting them with equipment for pumping ground water via casing column)

  • Using casing pipes in wells for water lifting requires application of a special (pipeless water-lifting) device.
Описание практики и ее результаты

The river originates in Kyrgyzstan in Ak-Suu Glacier on the northern slope of the Turkestan Ridge 3,193 m above sea level.  The Ak-Suu ruins are located close to the river source.  Near the settlement of Karavshin, the river is called the same name.  Crossing the national border, the river merges with the Kshemysh River (Kshemyshsai) and, further on, the river receives the name of Isfara.

 Actions:

Establishment of stakeholder groups, i.e. Small Basin Councils (SBC) representing local authorities, NGOs, water users and local communities.  SBC secretariats independently hold internal semi-annual meetings.  Thus, the SBCs serve as platforms to exchange opinions and information as well as take joint decisions associated with the enhancement of the overall situation in the river basin.

Results:

Creation of national Small Basin Councils (SBC) on the Isfara River allowed a platform for exchanging opinions and information as well as for drawing joint decisions to improve the overall situation in the Isfara River Basin, including the development of the IWRM basin plan for the target basin.

The pipeless water-lifting device allows fixing the submersible pump at a set depth and dividing the well’s trunk into suction and injection zones.

Water lifting is done via the casing column and not the water-lifting pipe used in traditional well operation technology.

 At the same time:

  • metal consumption and total weight of the pumping installation decreases by 60-90%;
  • pollution of the water-bearing layer is excluded; assembly and dismantling costs decrease by 40-70%;
  • power costs of water lifting decrease by 30%; water return of the water-bearing layer increases; possibility of polluting and/or infecting the water-bearing table is excluded making the suggested technology competitive.

 This technology of pumping underground water renders the possibility of intensifying water withdrawal due to creating vacuum in the pump’s suction zone.

Какие уроки и рекомендации можно извлечь из практики

Lessons learnt:

Introduction of IWRM principles is the pre-requisite of stable and fair water supply irrespective of a given water user’s location.

Recommendations:

Currently, when local stakeholders are represented in SBCs and are engaged in joint water management, it is necessary to hold thematic seminars to ensure sustainability of SBC operations in the future.  In the long term, it might be possible to establish a joint body to manage the whole river basin.

There is a need to perform major repair of vertical drainage system with the aim of ensuring the timely diversion of drainage and waste water from the Maktaaral Irrigation Massif.

It is also necessary to identify the optimal environmental and reclamation conditions to prevent salination of irrigated massifs by way of re-using drainage water for irrigation.

The data on the chemical composition of drainage and waste water (as per reports by Southern Kazakhstan Hydro-Geological Reclamation Expedition) prove that in most cases such water can used for irrigation without the need to dilute it with clean irrigation water.

Required personnel capacity-building:

  • continuous training of the staff of the Operational Section of Southern Kazakhstan branch of RSE “Kazvodkhoz” on assembly and dismantling of target equipment used for VDW re-fitting;
  • drafting and disseminating training materials (operation recommendations, practical seminars and trainings).
Источник практики

Foreign tools (transfer of foreign experience)

Domestic tools (outcomes of research by domestic R&D organizations)

Готовность практики к внедрению

1. Затраты на внедрение: Высокие

2. Примерная стоимость капиталовложений на 1 га:

3. Затраты на поддержание и эксплуатацию: Высокие

4. Экспертная поддержка: Не требуется

1. Затраты на внедрение: Высокие

2. Примерная стоимость капиталовложений на 1 га:

3. Затраты на поддержание и эксплуатацию: Высокие

4. Экспертная поддержка: Не требуется

Краткая информация о проекте

Development and implementation of basin plans constitute principal elements of integrated water resources management.  Multi-agency coordination mechanism via basin councils or coordination groups is an important advantage of IWRM.  This approach allows streamlined coordination and synergy of actions on all levels of management hierarchy.

Project title: Stakeholder partnership in joint policy-making: assistance to transboundary cooperation in small watersheds of Central Asia.

Project duration: Apr 2012-Oct 2016

Project goal and objectives: introduction of the integrated water resources management (IWRM) practice in three transboundary watersheds and its scaling-up in Central Asia.

Project beneficiaries: communities of the Isfara small transboundary river basin, specialists of water and environmental agencies, farmers.

Project implementer: USAID/CAREC.

Within the framework of 5039GF/4 Project supported via the financial grant on behalf of the Ministry of Education and Science (MoES) of Kazakhstan, several demo-sites were established in Maktaaral District of Southern Kazakhstan Region to hold trainings and practical seminars for specialists and to promote the new technology of pumping underground water via vertical drainage wells re-fitted with pipeless water-lifting devices.

Observations of ground water level were performed in the irrigation massif; optimal reclamation regime for irrigated land via vertical drainage wells based on the new technology was developed.

Источник финансирования практики USAID The technology was deployed under the grant project endorsed by the MoES of Kazakhstan
Источники информации о практике

carecnet.org

Tumlert, V.A., Tumlert, E.V. “Outcomes of designing a device to pump underground water via well casing column” //Fair and rational use of natural resources – a way to the future (III Urkumbayev Readings): report abstract for scientific and technical conference, Taraz 2015, pp. 337-347;

Amangeldiyev, S.S. “Power-and-resource-saving technology of pumping underground water via well casing column with submersible pumps” // Khabar TV Channel, “Innovative Overdrive” Program (in the Kazakh and Russian languages), May 2015;

Tumlert, V. A., Yugai, I.A., Telgarayeva, G.E., Tumlert, E.V. “Introducing a new resource-saving technology of operating vertical drainage wells in irrigated massifs of Southern Kazakhstan Region” // ”Agrarian Science in Agriculture of Siberia, Kazakhstan, Belarus and Bulgaria”: report at the XIX International Scientific and Technical Conference, Minsk 2016, pp. 183-188;

Tumlert, V. A., Yugai, I.A., Ismailov, B.D. “Technology of  pumping drainage water within the vertical drainage system in the irrigation massif of Southern Kazakhstan Region” // “Transboundary cooperation in Central Asia – stability and wellbeing of the whole region”: materials of international scientific and technical conference, Almaty 2017, pp. 181-187;

Tumlert, V. A., Yugai, I.A., Ismailov, B.D. “Intensifying water supply of distant pastures based on GIS-technologies” // “Prospects of innovative and investment development of the water sector”: materials of international scientific and technical conference, Kherson, Ukraine, May 18-19, 2017, pp. 133-137.

Контактные данные лица, заполнившего форму

SIC ICWC

SIC ICWC

Дата заполнения формы 02.04.2018 18.05.2018

Партнеры